CASE STUDY

Wastewater Treatment Plant for Northgate Estate in Harare, Zimbabwe

A flexible 3 MLD wastewater treatment plant designed to support Northgate Estate’s changing wastewater flows and produce treated water for irrigation reuse.

LOCATION

Harare, Zimbabwe

INDUSTRY

Residential Development

PLANT CAPACITY

3 MLD – 2 × 1.5 MLD Treatment Trains

FINAL WATER USE

Irrigation

PROJECT OVERVIEW

Flexible wastewater treatment for a growing residential development

Northgate Estate required a wastewater treatment solution capable of treating wastewater to a final quality compliant with Zimbabwe Standards. The development also required operational flexibility so that treatment capacity could be adjusted according to changing wastewater flows.

SewTreat proposed a 3 MLD wastewater treatment plant comprising two independent 1.5 MLD treatment trains. The system can accommodate wastewater flows from approximately 250 KLPD up to the full 3 MLD capacity, while the treated final water is designed for reuse in irrigation.

Wastewater Treatment Overview

TOTAL CAPACITY

3 MLD

CONFIGURATION

2 × 1.5 MLD Treatment Trains

OPERATING RANGE

Approx. 250 KLPD – 3 MLD

FINAL APPLICATION

Irrigation

THE CHALLENGE

Wastewater treatment capacity needed to scale with the development

Northgate Estate required more than a fixed-capacity wastewater treatment plant. As wastewater flows changed with the development, the treatment system needed to maintain reliable performance while allowing effective treatment capacity to be increased or reduced according to demand.

At the same time, the final treated water needed to meet the required Zimbabwe Standards and provide a suitable resource for irrigation reuse.

Treat wastewater to the required Zimbabwe Standards
Accommodate changing wastewater flow requirements
Provide sufficient capacity as the development grows
Produce treated water suitable for irrigation

FLEXIBLE TREATMENT CAPACITY

Designed Around Changing Wastewater Flows

250 KLPD

Approx. lower operating capacity

3 MLD

Maximum treatment capacity

2 × 1.5 MLD

Independent treatment trains

IRRIGATION

Final water use

Harare, Zimbabwe | Residential Development

3D render of Northgate Estate 3 MLD wastewater treatment plant in Harare, Zimbabwe

SEWTREAT’S SOLUTION

A 3 MLD wastewater treatment plant with two flexible treatment trains

SewTreat proposed a 3 MLD wastewater treatment plant comprising two independent 1.5 MLD treatment trains.

Each treatment train incorporates supplementary flow-through piping at the lower levels. This allows the effective treatment capacity to be reduced when required, giving Northgate Estate the flexibility to operate the plant according to actual wastewater flows rather than continuously operating at maximum capacity.

The configuration enables an operating range from approximately 250 KLPD up to the full 3 MLD capacity. Treated final water is designed to comply with Zimbabwe Green Normal Standards and can be reused for irrigation.

Operating capacity: approximately 250 KLPD – 3 MLD

SYSTEM CONFIGURATION

How the flexible wastewater treatment solution works

The two-train configuration allows Northgate Estate to match treatment capacity more closely with changing wastewater flows.

01

Two Treatment Trains

Two independent 1.5 MLD treatment trains provide a combined maximum treatment capacity of 3 MLD.

02

Supplementary Flow-Through Piping

Flow-through piping at the lower levels allows the effective capacity of each treatment train to be reduced when required.

03

Flexible Operating Range

The plant configuration can accommodate wastewater flows from approximately 250 KLPD up to 3 MLD.

04

Treated Water for Irrigation

Final treated water is designed to comply with Zimbabwe Green Normal Standards and can be reused for irrigation.

PLANT BENEFITS

Flexible wastewater management for long-term development needs

The Northgate Estate wastewater treatment plant combines high treatment capacity with operational flexibility and the ability to reuse treated water for irrigation.

01

High-Capacity Treatment

Provides total wastewater treatment capacity of up to 3 MLD.

02

Independent Treatment Trains

Two 1.5 MLD treatment trains provide greater operational flexibility.

03

Flexible Flow Management

Accommodates flows from approximately 250 KLPD up to 3 MLD.

04

Standards-Aligned Final Water

Final water is designed to comply with the required Zimbabwe Standards.

05

Irrigation Reuse

Treated wastewater can be reused as a water resource for irrigation.